The project "Magistral aqueduct for Bardar, Rusestii Noi" resumes

By the end of March, the works will be resumed within the project "Magistral aqueduct for Bardar, Ruseştii Noi (phase 2) and sewerage networks for the town of Ialoveni", reports Moldova 1.

According to the local source, the works foresee the construction of a sewage pumping station in the town of Ialoveni and about 7.6 km of sewerage. After the completion of this sub-project, approximately 1,700 inhabitants will have access to the reconstructed sewerage system.

The amount of the business contract is about six million lei. Up to now, the sum of about 1.9 million lei has been spent, of which 2.5 km of sewerage was built.

The project is also supported by development partners. Thus, according to an agreement, the amount of the grant provided by the Government of Slovakia amounts to 100,000 euros and the contribution of the Slovak Regional Development Agency Senec-Pezinok is 20,000 euros.